# Whakatāne Long Term Plan briefing weighs $5.2m Herepuru Road and $1.4m Keepa Road works alongside papakāinga contribution relief

> Ahead of 10 December budget decisions, a 19 November 2026 Whakatāne District Council briefing pack models subsidy-dependent Herepuru Road and Keepa Road Shared Use Path upgrades, recommends remitting non-water development contributions on up to 20 papakāinga dwellings per Māori land block, and drops $750,000 in five-year Awakeri operational funding.

- **Publication:** The Civic Record (Wellington, New Zealand)
- **Desk:** Local Government & Three Waters
- **Kicker:** WHAKATĀNE DISTRICT COUNCIL · LONG TERM PLAN 2027–37
- **Byline:** Local Government Desk
- **Published UTC:** 2026-11-17T11:00:00.000Z
- **Canonical URL:** https://civicrecord.nz/article/whakatane-long-term-plan-transport-development-contributions-scenario-2/

---

## Key Figures

- **Herepuru Road capex:** $5.2m — Modelled 2028–2029 total budget assuming 64% NZTA subsidy ($3.3m) and $1.8m council funding
- **Keepa Road path capex:** $1.4m — 2029 concrete renewal and rip-rap option assuming NZTA/BOPRC co-funding (~$468k WDC share)
- **Awakeri gateway cut:** $750k — Five-year operational expenditure removed from Scenario 2 draft planning
- **Recovery period cap:** 30 years — Recommended hard maximum cost-recovery period under Development Contributions Policy

Whakatāne District Council's 19 November 2026 Long Term Plan (Te Mahere Pae Tawhiti 2027–37) briefing sets out modelled capital options for Herepuru Road and the slumping Keepa Road Shared Use Path, seeking councillor direction on nine Development Contributions Policy choices and Scenario 2 non-waters budget changes ahead of bulk budget decisions on 10 December 2026. For Herepuru Road, staff suggest $20,000 to $50,000 in existing 2026/27 operational expenditure for concept scoping and $200,000 in Year 1 for design and planning, while LTP modelling budgets $5.2 million total capital expenditure in 2028 and 2029—assuming a 64 per cent NZTA subsidy ($3.3 million) and $1.8 million in council funding, with annual debt servicing costs of roughly $140,000 (0.02 per cent of 2027 rates revenue).

On the Keepa Road Shared Use Path, worsening bank slumping along section 3 from open flood gates over roughly the past five years and tidal erosion—compounded by contaminated material costing $10,000 for testing alone—will eventually affect the road if left unresolved. Staff model a preferred 2029 (Year 2) option of concrete path renewal (approximately $1.2 million) combined with rip-rap bank protection for a $1.4 million total capital budget, assuming 64 per cent NZTA subsidies on the concrete path ($768,000) and remaining rip-rap ($64,000) alongside a 50 per cent Bay of Plenty Regional Council rip-rap contribution ($100,000), leaving approximately $468,000 in council funding (roughly $300,000 from renewals and $168,000 from development contributions). If NZTA funding is not obtained, staff note chipseal resurfacing at roughly $300,000 from renewals could be considered.

Under the Development Contributions Policy review, staff seek direction on nine policy settings before modelled dollar charges are finalised after the LTP programme is refined. Staff recommend measuring residential demand by bedrooms (0.50 household equivalent units for one-bedroom homes, 0.75 for two bedrooms, and 1.00 for three or more bedrooms) with safeguards or improved floor-area thresholds; adopting targeted papakāinga relief remitting transport, reserves, and community charges on the first 20 dwellings per Māori land block while keeping water payable; applying lower evidence-based factors to legally secured retirement units and aged-care beds; confirming a hard 30-year maximum cost-recovery period; retaining Financial Contributions alongside DCs for unplanned local effects; aligning common definitions and policy rules with Ōpōtiki District Council while keeping local charges separate; and requiring any DC reduction to have an explicitly named funder (such as general or targeted rates, grants, or scope changes) with no unfunded cap.

On the non-waters draft budget, the Scenario 2 list stands at 105 progressed gateways as at 19 November—up from 85 on 12 November, with overall totals including waters gateways progressing separately—while executive leadership recommends staging or trimming specific bids. The Awakeri Fastrack Gateway (#175) has been removed, cutting $750,000 in total operational expenditure over five years (though staff note it can be re-added later); leadership also recommends staging the Whakatāne Aquatic Centre café relocation (#162) and Event Space (#109) while pausing the PVC membrane (#115) and bulkhead (#163) to the next Annual Plan, reducing the CCTV budget (#152) to $60,000 per annum, excluding the Ōhiwa Mountain Bike Park (#99) from draft budgets while consulting the community, phasing five public toilet projects across Years 2 to 6, trimming mayoral internships from three to one, and dropping nine Scenario 1 proposals. Community consultation on the LTP is scheduled from 1 April to 1 May 2027 ahead of June 2027 adoption.

## Primary Sources

- **Whakatāne District Council** (19 Nov 2026): 12:30 pm Council Briefing: Long Term Plan — [Original Document](https://www.whakatane.govt.nz/sites/www.whakatane.govt.nz/files/documents/2026-11/council-briefing-long-term-plan-19-november-2026.pdf)