# Wellington City Council committee adopts modified Brooklyn Connections bike and bus traffic resolution, retaining Ōhiro Road parking within $4.1 million budget cap

> Te Takere | Regulatory Processes Committee approves detailed design and construction for the Brooklyn to City corridor using narrower 300mm cycle-lane separators, while directing officers to consult in early 2027 on a weekday morning clearway and an extended 30km/h speed limit.

- **Publication:** The Civic Record (Wellington, New Zealand)
- **Desk:** Local Government & Three Waters
- **Kicker:** LOCAL GOVERNMENT · TRANSPORT INFRASTRUCTURE
- **Byline:** By the Local Government Desk
- **Published UTC:** 2026-11-24T22:17:53.286Z
- **Canonical URL:** https://civicrecord.nz/article/wcc-adopts-brooklyn-connections-traffic-resolution/

---

## Key Figures

- **Approved budget cap:** $4.1m — Construction to proceed only within approved budget and agreed scope
- **West-side parking retained:** ~20 spaces — City-bound side of Ōhiro Road between Todman Street and Brooklyn Road
- **Cycle-lane separators:** ~300mm — Reduced from proposed 600mm separators where safety standards are met

Wellington City Council’s Te Takere | Regulatory Processes Committee has adopted a modified traffic resolution for the Brooklyn Connections biking and bus improvements project, clearing the scheme to proceed to detailed design and construction subject to remaining within its approved $4.1 million budget and agreed scope.

Following public consultation and oral submissions considered at its 7 October 2026 meeting, the committee resolved to amend the proposed corridor along Brooklyn Road and Ōhiro Road to retain and reinstate several on-street parking sections and adjust cycle-lane separator widths. According to implementation updates recorded on 11 November 2026, detailed design incorporating the committee's changes is now underway.

Under the amended design, the council will retain the existing approximately 20 parking spaces on the city-bound west side of Ōhiro Road between Todman Street and Brooklyn Road, retain or reinstate up to eight car parking spaces on the east side of Ōhiro Road opposite Tanera Crescent and Cleveland Street, and retain existing parking spaces outside 169 to 175 Ōhiro Road. The committee also agreed to retain existing bus stop 6718 outside 159A Ōhiro Road in its current location, retain the existing length of bus stops 6716 and 7718, and remove existing bus stop 6719 outside 183 Ōhiro Road, adding up to four parking spaces outside 181 to 185 Ōhiro Road.

Rather than installing the originally proposed 600mm cycle-lane separators, the committee agreed to use approximately 300mm-wide separators where safety standards are met, consistent with treatments used in Auckland and Christchurch. The detailed design phase will also include pedestrian access.

Alongside the adopted traffic resolution, the committee directed council officers to develop designs and consult on further traffic resolutions to introduce a 7.00am to 9.00am weekday clearway on the city-bound side of Ōhiro Road, as well as to consult on extending the 30km/h speed limit on Ōhiro Road to the north of Tanera Crescent. Review work on both measures is underway, with public consultation expected to take place early in 2027.

## Primary Sources

- **Wellington City Council (Te Kaunihera o Pōneke)** (25 Nov 2026): TR67-26 Brooklyn to City, Bike and Bus Improvements - Traffic Resolution Approval Te Takere | Regulatory Processes CommitteeMeeting Date: 07 Oct, 2026This report to Te Takere | Regulatory Processes Committee seeks approval of a modified traffic resolution reflecting the outcomes of the public consultation on the Brooklyn Connections biking, and bus improvements project as well as approval to proceed to delivery of the project. — [Original Document](https://meetings.wellington.govt.nz/your-council/reports/2058/TR67-26%20Brooklyn%20to%20City%2C%20Bike%20and%20Bus%20Improvements%20-%20Traffic%20Resolution%20Approval?Stage=Final+decisions)