Waitomo District Council reports $9.6 million accounting surplus in draft 2025/26 annual report as $83.7 million in water assets and $32.6 million in debt transfer to Waikato Waters Limited

Three storm events expanded the roading capital programme from a planned $8.0 million to around $15.4 million, while the council closed its last landfill cell and submitted a King Country unitary authority proposal alongside Ōtorohanga District Council.

$83.74m
Water assets transferred
Water supply and wastewater assets transferred to Waikato Waters Limited on 1 July 2026
$32.56m
External debt transferred
Settled with LGFA on 1 July 2026 against total borrowings of $38.28m at 30 June 2026
$15.37m
Roading capital spend
Against an $8.01m budget following storm damage in July 2025, October 2025, and April 2026
$54.3m
Total revenue
Against a $44.3m budget, yielding a $9.6m non-cash accounting surplus

Waitomo District Council recorded an operating accounting surplus of $9.6 million for the year ended 30 June 2026 in its draft 2025/26 annual report, before completing a post-balance-date transfer of $83,738,000 in water supply and wastewater assets and $32,564,000 in associated external debt to the multi-council organisation Waikato Waters Limited on 1 July 2026. The council notes that the $9.6 million operating surplus is an accounting surplus rather than a cash surplus, driven primarily by capital expenditure subsidy and grant revenue and offset in part by not fully rate-funding depreciation expense.

Total revenue for the 2025/26 financial year reached $54.3 million against a budget of $44.3 million, including $21.7 million in subsidies and grants. Total expenses were $45.2 million against a budget of $43.2 million. Total equity at 30 June 2026 stood at $706.2 million—$14.4 million below the $720.6 million forecast—principally because the revaluation reserve was $31.9 million lower than budgeted. While the budget had assumed a $31.5 million gain on the revaluation of road assets, the actual valuation resulted in a $0.5 million loss due to pavement formation unit rates remaining unchanged after three years of additions at higher unit rates.

On 1 July 2026, Waitomo, Waipa, and South Waikato district councils completed the transfer of their drinking water and wastewater operations, staff, assets, and liabilities to Waikato Waters Limited. Incorporated on 24 July 2025, the council-controlled organisation is jointly owned by Hauraki, Matamata-Piako, Ōtorohanga, South Waikato, Waipa, and Waitomo district councils. Waitomo District Council was issued 4,944 stage-two voting shares, representing 5 per cent of total shares on issue, proportionate to its number of connections. Once the remaining three shareholding councils complete their transfers, Waikato Waters Limited will oversee 50,000 connections, 60 treatment plants, and 3,300 kilometres of pipes across the greater Waikato and Hauraki Plains region. Any profits generated must be reinvested or used to reduce debt, and distributions to shareholding councils are prohibited.

Prior to the 1 July 2026 transfer, Waitomo District Council's total borrowings stood at $38,280,000 ($38.3 million) at 30 June 2026, with net debt of $32.6 million representing 60 per cent of total revenue against the council's 165 per cent Financial Strategy limit. On the transfer date, Waikato Waters Limited paid cash to the council that was immediately applied to the New Zealand Local Government Funding Agency to settle $32,564,000 of water and wastewater debt. A final wash-up calculation of transferred assets and debt is scheduled for November 2026 once annual reporting balances are finalised. Under the transfer arrangements, Waitomo District Council will continue billing for water and wastewater services in 2026/27 as a rate under the Local Government (Rating) Act 2002 before Waikato Waters Limited assumes direct billing through fees and charges in 2027/28, subject to Commerce Commission economic regulation. The council notes that the financial impact on ratepayers for both Waikato Waters Limited's charges and the council's rates for remaining services remains uncertain.

Total capital expenditure across the council reached $24,836,000 ($24.8 million) against an approved budget of $22,041,000 ($22.0 million). Three severe weather events in July 2025, October 2025, and April 2026 expanded the roads and footpaths capital programme from a budgeted $8,007,000 to $15,369,000, supported by over $21.4 million in New Zealand Transport Agency subsidies across maintenance, renewals, and recovery. Recovery from the July 2025 storm was completed during the year with $7.5 million in agency funding, including road retreats on Mangatoa and Manganui Roads, five retaining walls, and two buttresses. The October 2025 storm damaged 120 sites across the network; New Zealand Transport Agency approved $5.13 million for phase-one emergency repairs and the investigation and design of 23 complex sites, while Kopaki Road remains closed at the RP 4.8 landslide pending reinstatement options. Alongside storm recovery, the council resurfaced 29.4 kilometres of sealed road (6.4 per cent of the sealed network, above the 5 per cent target) and metalled 98.3 kilometres of unsealed road (17.9 per cent, meeting the 15 per cent target).

In water supply, capital expenditure totalled $6,091,000 against an $8,327,000 budget. Physical works on the Te Kūiti Water Resilience Project began in February 2026, including laying a rising main pipeline along Rora Street toward the Hospital and Hetet reservoirs, demolishing the existing Hospital reservoir, and constructing foundations for its replacement. The project and its associated contracts transferred to Waikato Waters Limited on 1 July 2026 and remain scheduled for completion in November 2026.

In solid waste, where capital expenditure was $575,000 against a $2,650,000 budget, the council closed the last waste cell at the Waitomo District Landfill on 30 June 2026 following declining waste volumes and a June 2025 decision not to develop the next cell. From 1 July 2026, all district waste streams are managed for transport to out-of-district facilities. Following a month-long consultation and a public meeting in Mōkau in April 2026 where most submissions opposed relocating the Awakino Transfer Station to an industrial site on Oha Street in Mōkau, the council decided not to proceed with the move, and the planned Te Kūiti transfer station improvement project also did not proceed as originally planned due to lower expected waste volumes and a lack of central government funding.

On local government reorganisation, elected members unanimously resolved on 26 May 2026 to develop a voluntary Head Start amalgamation proposal with Ōtorohanga District Council under the Government's Simplifying Local Government programme. The two councils submitted an outline proposal supporting the establishment of a single unitary authority for the King Country. Cabinet is expected to consider Head Start proposals in early 2027, with any approved changes intended to take effect before the 2028 local elections; if the proposal is not accepted or no final proposal is approved, the council may be subject to a compulsory backstop reform process after the 2028 elections, the detailed design and financial impacts of which remain unconfirmed.