LOCAL GOVERNMENT · CIVIC FACILITIES

Waitomo District Council tables $225,000 feasibility budget for Les Munro Centre revitalisation as community feedback opposes library relocation

A report to Council outlines a broad conceptual capital cost estimate of $4.7 million to $5.4 million for the full revitalisation and proposes redirecting unspent Better-Off Funding to cover concept and preliminary design through to June 2027.

$4.7m – $5.4m
Broad revitalisation estimate
Conceptual capital cost estimate including space for a new build to accommodate the library
$225,000
Proposed feasibility budget
Estimated project cost to 30 June 2027, bringing total feasibility project cost to $265,000
$3.141m – $4.648m
2025 initial option costings
Indicative capital costs from June 2025 across core, theatre upgrade, and library extension options

Waitomo District Council is considering whether to approve a further $225,000 budget to advance feasibility and preliminary design work for the revitalisation of the Les Munro Centre, following a community engagement programme that showed broad support for upgrading the venue but opposition to relocating the Waitomo District Library into the building.

In a business paper prepared for the Council's 29 September 2026 meeting, Chief Executive Ben Smit presented three formal options: stopping the feasibility project completely, pausing the next stage while the Les Munro Centre Steering Group oversees further concept and business case development, or approving the feasibility project to continue through to June 2027 with a budget of $225,000.

According to the report, a very broad, conceptual estimate of the capital cost to complete the revitalisation project is $4.7 million to $5.4 million, derived by inflating earlier scoping work and adding space for a new build to accommodate the library. During an initial project phase completed in June 2025, three indicative capital cost options were developed: $3.141 million for a core upgrade, $3.571 million for a core and theatre upgrade, and $4.648 million for a core, theatre upgrade, and library extension.

To fund the $225,000 required for the next feasibility stages through to 30 June 2027—on top of $40,000 already committed for initial project costs to 30 September 2026—the paper proposes combining $119,000 in uncommitted Better-Off Funding already retained for the Les Munro Centre with $146,000 reallocated from a $200,000 Sports Development Better-Off Funding sub-project. That $200,000 allocation had originally been repurposed on 30 April 2024 from a Methamphetamine Programme to the Sports Development sub-project, which subsequently proved unable to reach key project milestones. Under the proposed funding split, the remaining $54,000 from the sport coordinator fund could be applied to an unallocated tranche and directed toward stormwater improvements, which currently have $1.5 million of funding allocated.

The report notes that the Better-Off Funding grant is now administered by the National Infrastructure Funding and Financing department (NIFF). While previous Department of Internal Affairs advice in October 2024 indicated that reallocating funds within the Social Good or Town Amenity groupings did not require project change approval beyond reporting disclosure, the paper identifies a low risk that a new NIFF relationship manager could take a different view. By contrast, reallocating the funding toward stormwater projects is assessed as carrying almost no risk, and any Better-Off Funding must be spent before June 2027.

If Council approves the $225,000 feasibility budget under Option 3, the funding will cover predesign, concept design (largely by architect Boon Ltd with cultural support and a quantity surveyor), preliminary design with geotechnical, structural, services, and fire specialists, and support for sourcing external funding. The report sets out three subsequent decision gateways where expenditure could still be halted: November 2026, when an estimated capital budget goes to Council for inclusion in the draft 2027–37 Long Term Plan; March 2027, when the Long Term Plan engagement document and budget are approved; and June 2027, when the final Long Term Plan is adopted.

Community engagement conducted from late August to late September 2026—comprising an open day on 28 August, Social Point online tools, a dedicated library survey, website and paper forms, and Facebook comments—found broad support for revitalising the dated and underutilised centre, which had been discussed with stakeholders including the Shearing Committee, Te Nehenehenui, On-Stage Te Kūiti, and the Waitomo Society of Arts. However, the feedback summary concludes there is no evidence of broad support for relocating the library, with community preference on balance favouring its retention at its current site. Respondents cited concerns over losing the current library's quiet, central atmosphere, potential disruptions from weddings, funerals, the Shears, and concerts, practical challenges around heating and storage, and the rates impact of spending millions during a period of high rates pressure.