# Waitomo District Council tables $6.96m capital carry-forward into 2026/27, lifting revised capital programme to $29.7m

> Storm damage road renewals and Te Kuiti landfill capping account for the largest portions of unexpended 2025/26 project budgets recommended for transfer, alongside $96,000 in reallocated audit fees.

- **Publication:** The Civic Record (Wellington, New Zealand)
- **Desk:** Local Government & Three Waters
- **Kicker:** LOCAL GOVERNMENT · CAPITAL PROGRAMME
- **Byline:** The Civic Record Local Government Desk
- **Published UTC:** 2026-11-24T19:36:58.557Z
- **Canonical URL:** https://civicrecord.nz/article/waitomo-district-council-tables-6-96m-capital-carry-forward/

---

## Key Figures

- **Proposed capital carry-forward:** $6,960,700 — Unexpended 2025/26 capital project budgets recommended for transfer to 2026/27
- **Revised 2026/27 capital programme:** $29.7m — Includes $24 million (81 per cent) in forecast roads capital expenditure
- **Roads capital carry-forward:** $4,463,400 — Includes $3,504,400 for July and October 2025 storm damage renewals
- **Operational carry-forward:** $96,000 — Unspent 2025/26 audit fees reallocated to IT consultant fees

Waitomo District Council staff have tabled a business paper for the council's 25 August 2026 meeting seeking approval to carry forward $6,960,700 in unexpended 2025/26 capital budgets and $96,000 in operational budgets into the 2026/27 financial year. Prepared by Chief Financial Officer Tina Hitchen, the proposed carryovers would lift the council's total revised capital programme for 2026/27 to $29.7 million. Of that revised total, forecast roads capital expenditure accounts for $24 million, or 81 per cent, including emergency reinstatement and storm event repairs largely funded from NZTA.

According to the report, several 2025/26 projects and programmes were either incomplete at year-end or experienced delayed start dates due in part to contractor availability, weather conditions, internal resourcing, and the prioritisation of other work programmes. The proposed carry-forwards will not affect the adopted 2026/27 funding requirement because all transferred budgets already hold funding sources through subsidies, reserves, or debt, while rates for the incomplete operational programmes were collected during 2025/26.

Roading accounts for $4,463,400 of the proposed capital carryover. That figure comprises $3,504,400 to continue road renewals following the July and October 2025 weather events, $569,000 for storm damage renewals from the April 2026 event—reallocated from remaining unspent budgets for the 2022 and 2023 weather events—and $390,000 for ongoing roading renewals including structures component replacements and drainage works.

Solid waste projects account for $1,303,000 of the capital carryover, led by $1,003,000 for Te Kuiti landfill capping, which combines $597,000 from the original capping budget allocated in the 2026/27 Annual Plan with $406,000 reallocated from the original transfer station improvements budget. Further reallocated transfer station funds cover $250,000 for internal roading, pothole, and drainage renewals on the Te Kuiti transfer station accessway and $30,000 for Te Kuiti resource recovery centre capacity improvements funded from Waste Minimisation Levy funds, alongside $20,000 for weighbridge software and safety signage upgrades.

Stormwater projects represent $651,000 in proposed carryovers, comprising $191,500 for Te Kuiti stormwater main renewals and minor works, $173,000 for committed Te Kuiti stormwater improvements, $120,000 for Eketone Street stormwater works funded by Better Off Funding, $92,000 for Te Kuiti catchment management plan renewals, $51,000 for rural stormwater renewals combined with the 2026/27 allocation to deliver a viable programme, $14,500 for Te Kuiti stormwater resource consent renewal prior to lodgment with Waikato Regional Council, and $9,000 for rural catchment management plans.

The remaining capital carryovers comprise $416,700 in recreation and property—covering $315,400 for Eketone Street sections development under Better Off Funding and $101,300 for Centennial Park development—and $126,600 in leadership projects. Those leadership items include $54,000 for end-user device replacements following a 25 per cent rise in device costs over the past six months driven by a global shortage of RAM, $37,600 for weather-delayed aerial photography, $20,000 for connectivity improvements at council sites including transfer stations, and $15,000 for IT hardware renewals.

On the operational side, the report proposes carrying forward and reallocating $96,000 from the 2025/26 leadership audit fees budget. That allocation had been increased to cover an audit of an anticipated Long Term Plan amendment following the transfer of waters assets and services; after no amendment was required, the audit did not proceed, and staff recommend applying the unspent funds to IT consultant fees for workflow design, automation, and connectivity upgrades. The report notes that carrying the projects forward risks affecting the delivery of work already planned for 2026/27, whereas declining the carryovers carries reputational and service-level risks given rates for the projects have already been collected. The resolutions remain suggested until formally adopted by the council.

## Primary Sources

- **Waitomo District Council** (25 Nov 2026): Item 20 - 2025-26 Carry Forwards (PDF 144 KB) — [Original Document](https://www.waitomo.govt.nz/media/jh0mrwjf/item-20-2025-26-carry-forwards.pdf)