Waitomo District Council tables $40,000 Better-Off Fund allocation for Les Munro Centre pre-engagement as library co-location options advance

A paper for the 25 August 2026 meeting seeks retrospective budget endorsement for initial community consultation after elected members raised concern over committed expenditure, warning the remaining $116,000 grant balance is very unlikely to cover costs through June 2027.

$40,000
Proposed pre-engagement budget
To the end of September 2026 from the Better-Off Fund
$116,000
Uncommitted Better-Off Fund balance
Out of the $200,000 Les Munro Centre Revitalisation grant allocation as at 30 June 2026
$3,691,000
Total Better-Off and Tourism Infrastructure package
Across all Waitomo District Council grant project groupings, expiring 30 June 2027
1,500m²
Les Munro Centre total floor area
Including a 750-capacity main hall, 120-capacity supper room, and 100-capacity foyer

Waitomo District Council will on 25 August 2026 consider a suggested resolution from Chief Executive Ben Smit to endorse a $40,000 allocation from the Better-Off Fund for pre-engagement work on the Les Munro Centre revitalisation project. The business paper comes before the council after elected members expressed concern at a 30 June 2026 workshop and a 4 August 2026 briefing that the project had committed expenditure before a project budget had been approved.

Built in 1979 as the Waitomo Cultural and Arts Centre and renamed in 2015 after Second World War Dambuster pilot and former Waitomo Mayor Les Munro, the 1,500-square-metre venue comprises a 750-capacity main hall, a 120-capacity supper room, and a 100-capacity foyer. While the facility hosts the New Zealand Shearing Championships, funerals, and smaller community events, council papers note its overall usage is low and it costs ratepayers significantly more to operate and upgrade than it generates in revenue. At the same time, the council reports that its public library is bursting at the seams, prompting an investigation into whether the Les Munro Centre could be revitalised as a combined community and cultural hub incorporating library services.

Of the $200,000 originally allocated to the Les Munro Centre Revitalisation project from the council's wider $3,691,000 Better-Off Fund and Tourism Infrastructure Fund package, $84,000 had been spent as at 30 June 2026, leaving an uncommitted balance of $116,000. All projects under the Better-Off Fund grant must be completed with claims and supporting evidence filed and approved before the grant expires on 30 June 2027. While forecast pre-engagement costs to the end of September 2026 are within the proposed $40,000 allocation, the Chief Executive's report notes that a full budget through to 30 June 2027 is still being compiled and is expected to exceed the remaining $116,000 grant balance.

Initial scoping and three design concepts developed by Boon Limited in 2024—which followed a 30 July 2024 council resolution to put a new air-conditioning unit installation on hold pending a wider utilisation review, though the terms of reference note the air-conditioning upgrade has recently occurred—were paused in 2025 to be reconsidered through the Long-Term Plan process. After the project resumed in 2026 under a steering group chaired by Mayor John Robertson alongside Deputy Mayor Eady Manawaiti and Councillors Olivia Buckley and Isaiah Wallace, staff launched the interactive Social Point engagement platform and scheduled a community open day at the venue for 29 August 2026. The engagement seeks public feedback across five broad activity categories: art, culture, and history celebration; an education and learning centre; access to technology; spaces to meet and hold social gatherings; and physical spaces for meetings and activities, while retaining event space for the New Zealand Shearing Championships and larger funerals.

The Chief Executive advises that stopping the revitalisation project before the 29 August open day would yield little or no financial saving and could create confusion given the promotional and engagement work already undertaken. Feedback from the initial engagement will be brought to the 29 September 2026 council meeting for a formal decision on whether to proceed with conceptual design and costing for inclusion in the 2027–2037 Long-Term Plan consultation scheduled for March and April 2027.