Waitomo District Council has outlined a $19.58 million roading capital programme for 2026/27—of which $10.5 million is dedicated to storm recovery—alongside an approximate $10 million construction schedule for October 2025 storm damage and geotechnical assessment of options to reinstate the landslide-closed Kopaki Road.
In a bi-monthly roading activity report prepared for the council's 24 November 2026 meeting by Roading Manager Richard Shailer and Manager Solid Waste – Operations and Contracts Komal Devi, staff report that an updated funding application for the October 2025 storm was resubmitted to the New Zealand Transport Agency (NZTA) on 29 October after the agency asked for simpler, lower-cost repairs on roads carrying very little traffic. About $6 million of construction is planned over the next six months, with a further $4 million or so to follow, most of it in 2027/28. NZTA's 95 per cent funding rate for the October 2025 storm runs until 30 June 2028.
This summer's storm repairs cover about 16 sites, mostly in the western and southern hill country, grouped into contracts for road retreats, retaining walls and stream erosion repairs. The contracts are currently in tender, with the first expected to be awarded in early December and the remainder before Christmas for construction running until about the end of March 2027, subject to NZTA approving the October 2025 funding. To date, NZTA has approved storm repair funding of $2.81 million and $4.665 million for the Winter 2025 storm, $5.13 million for the October 2025 storm, and $545,000 for the April 2026 storm.
Two roads across the district's network of 459 kilometres of sealed roads and 547 kilometres of unsealed roads remain closed: Kopaki Road due to a landslide and Mokauiti Road due to an underslip. At Kopaki Road, where barriers and weekly monitoring are in place, council staff are considering an initial price from contractor Inframax Construction Limited to rebuild the road through the slip on its existing line, after a realignment was priced at $6.6 million in February. The report notes that rebuilding on the existing line is a higher-risk option because the road would be constructed through slip material below a slope that still has cracks.
NZTA confirmed on 5 November that if the existing-line rebuild proceeds, it can be funded as a storm repair at the 95 per cent subsidy rate rather than requiring a new business case. An independent geotechnical review of Inframax's method—estimated in council Long Term Plan workshop records at under $20,000—will be completed before options are brought back to a council workshop, where elected members will weigh reinstatement costs against permanent closure paired with a $994,375 upgrade of the Pukerimu Road detour.
On Manganui Road, a contract to rebuild the first 1.7 kilometres is expected to be awarded before Christmas. To address river damage along Manganui Road, the council has directed staff to pursue a single Waikato Regional Council resource consent for a permanent realignment of the river's low-flow channel, starting with the two worst reaches, while continuing interim repairs under the maintenance contract and including $1 million in the draft Long Term Plan in 2028/29 for the river realignment.
Looking ahead to the 2027–37 Long Term Plan, the council is preparing a draft 2027–30 roading funding bid of about $55 million over three years, supported by a 75 per cent NZTA funding assistance rate, which is due with NZTA on 11 December 2026. Following workshop direction, staff have proposed adding about $850,000 a year to the bid—of which the council's local share would be about $212,000 a year—to fund all urgent and high-priority bridge and culvert repairs and line eight steel culverts before they fail. Meanwhile, the share of travel on smooth sealed roads has fallen from 97 per cent to 90 per cent, and forestry harvest traffic is speeding up wear on affected roads. A draft approach for managing forestry harvest traffic, prepared after the 15 September workshop, is with the Chief Executive for review. The roading team is also looking at lower-cost seal types where they suit the road, after the NZTA audit found single-coat seals on the network are lasting almost twice as long as two-coat seals.