TIAKI WAI · METROPOLITAN WATER INFRASTRUCTURE

Tiaki Wai expands Wellington region pipe renewals to 35–49km after assuming direct water billing from councils

Metropolitan water provider Tiaki Wai plans to renew between 35 kilometres and 49 kilometres of pipes in 2026/27—up from 11 kilometres completed last year—with around $200 million going directly into replacing ageing and failing water infrastructure across Wellington, Porirua, Lower Hutt, and Upper Hutt.

35 km to 49 km
2026/27 Renewal Target
Planned regional pipe renewals in 2026/27, compared with 11 km completed in 2025/26
Around $200m
Direct Capital Spend
Allocated directly to replacing ageing and failing pipes and critical water infrastructure this financial year
Nearly 1,000 km
Expired Network Pipes
Share of the region's 6,800 km pipeline network past its expiry date, with some pipes over 100 years old

Tiaki Wai is expanding its Wellington region pipe renewal programme to tackle between 35 kilometres and 49 kilometres of pipes in 2026/27, up from 11 kilometres completed in 2025/26, with around $200 million going directly into replacing ageing and failing pipes and other critical water infrastructure this financial year. Delivering drinking water, wastewater, and stormwater services to around 155,000 homes and businesses across Wellington, Porirua, Lower Hutt, and Upper Hutt, the organisation oversees 6,800 kilometres of pipelines, four wastewater treatment plants, 345 pump stations, and 140 drinking water storage reservoirs. Nearly 1,000 kilometres of the region's pipes are past their expiry date—with some more than 100 years old—following decades of underinvestment.

Across its second-quarter customer updates for the four cities, Tiaki Wai detailed targeted wastewater and drinking water upgrades underway or recently completed. In Wellington's Crofton Downs, where an undersized 1962 pipe buried more than 10 metres beneath a filled gully under Churchill Drive overflows during wet weather into the Ōtari-Wilton's Bush carpark and Kaiwharawhara Stream, Tiaki Wai plans to use micro-tunnelling technology to drill a new wastewater line from the carpark to where the stream emerges just below Blackbridge Road and adjust nearby pipe layouts to divert flows downstream, working with Wellington City Council, Ōtari-Wilton's Bush Trust, Kia Mouriora te Kaiwharawhara, and mana whenua partners. In Porirua, over 2.6 kilometres of drinking water pipe have been replaced in Cannons Creek since January, most recently in Gloucester Street and Hereford Street, where pipes over 65 years old from the 1950s building boom had caused multiple drinking water outages over the last five years; crews replaced 1.3 kilometres of pipe and added new property-boundary connections in Gloucester Street to meet recent regulatory changes, alongside replacing a 120-metre problem section in Hereford Street in July with no leaks registered since.

In Upper Hutt, crews excavated open trenches supported by trench shields between April and the end of August to replace over 500 metres of deteriorated 1951 asbestos-reinforced concrete wastewater pipe across five separate road sections in Wyndham Road, Pinehaven, using asbestos-removal specialists before installing new uPVC pipes following repeated blockages. In Stokes Valley, contractors replaced about 15 metres of wastewater pipe—expected to last for 100 years—and relined 30 metres expected to last about 50 years along a narrow strip of land between two houses on Stokes Valley Road, completing the upgrade on time and to budget to reduce the risk of blocked or overflowing sewerage pipes near Tui Glen School.

The capital programme is partly funded through direct water services charges after Tiaki Wai took over responsibility for water services, replacing the water component paid through council rates before 1 July 2026. Customers are billed every three months—with properties that have existing water meters receiving separate bills for water services and metered usage—and Tiaki Wai stated that quarterly charges will remain unchanged for a year, confidential hardship support is available for residential property owners without water being turned off, and any price changes will follow consultation in March 2027 on a draft Water Services Strategy 2027 informed by customer survey feedback, legal and regulatory requirements, council owners, and mana whenua partners.