# Tauranga council staff table $37.3m Pāpāmoa tsunami evacuation programme with no confirmed funding beyond Domain Road and Parton Road

> Workshop reports prepared for Tauranga City Council seek endorsement of ten capital and operational tsunami evacuation projects after updated GNS modelling showed inundation reaching further inland at Pāpāmoa, while warning that NZTA will not fund evacuation routes and Council has deferred its citywide resilience fund beyond ten years.

- **Publication:** The Civic Record (Wellington, New Zealand)
- **Desk:** Local Government & Three Waters
- **Kicker:** TAURANGA CITY COUNCIL · HAZARD RESILIENCE & LONG-TERM PLAN
- **Byline:** Local Government & Hazards Desk
- **Published UTC:** 2026-11-16T14:32:52.320Z
- **Canonical URL:** https://civicrecord.nz/article/tauranga-papamoa-tsunami-evacuation-programme-funding-gap/

---

## Key Figures

- **Total Programme Estimate:** $37.3m — $36.805m capital and $0.51m operational across ten Pāpāmoa evacuation projects ($37,315,000 total)
- **Domain Road Upgrade:** $24m — Included in the 2027–2037 Long-term Plan, though deferred beyond the first three years on 11 November
- **Bruce Road Land Project:** At least $5m — Unfunded land purchase for a 5m-wide shared path linking south to the Tauranga Eastern Link
- **2026/27 City Centre Fund:** $233,250 — Final budgeted year of the City Centre Development Incentive Fund, down from $500,000 in 2021/22

Tauranga City Council staff have tabled a ten-project tsunami evacuation programme for Pāpāmoa estimated at $37.315 million—comprising $36.805 million in capital works and $0.51 million in operational projects—ahead of a Long-term Plan council workshop scheduled for Thursday, 19 November 2026. The programme responds to one-in-2,500-year tsunami modelling, including an August 2024 GNS evacuation bottleneck study and March 2025 GNS inundation mapping that underpinned new public "Blue Zone" evacuation maps released in April 2026. A November 2025 WSP review of the updated GNS modelling found tsunami flooding reaching further inland in several areas, with new flooding along Bell Road and in the Te Manawa o Pāpāmoa "dry island", and the largest inland expansion occurring in Pāpāmoa from Parton Road east to Stevenson Drive, where staff warn residents face a higher risk to life until routes, safe areas, and markings are updated.

The six proposed capital works are led by a $24 million full urban upgrade of a 600-metre section of Domain Road between The Gardens Drive and Tara Road—already included in the 2027–2037 Long-term Plan, though Council deferred it beyond the first three years on 11 November 2026—alongside at least $5 million to buy Bruce Road cornfield land (potentially via the Public Works Act) for a 5-metre-wide shared path to the Tauranga Eastern Link, a $3.8 million asphalt shared path on NZ Transport Agency (NZTA) land to Domain Road, a deferred $2.2 million Tara Road footpath widening and signalised crossing, $1.5 million for two drainage-swale bridges and three reserve paths, and a $0.305 million Parton Road footpath project. Four operational projects totalling $0.51 million cover pedestrian and vehicle movement modelling ($0.15 million), marking safe assembly zones with blue poles, bollards, signs, and pavement markings ($0.11 million), an updated mass-evacuation traffic management plan ($0.1 million), and a $0.15 million tsunami resilience assessment of State Highway 2 overbridges at Sandhurst and Parton, as older bridges probably do not meet current earthquake standards and no Tauranga bridges are expected to be designed for tsunami loads.

Aside from Domain Road and the $0.305 million Parton Road footpath (already in the Minor Safety and Accessibility programme), no funding source is confirmed for the remaining $1.5 million in minor improvements, $11.0 million or more in larger capital works, or $0.51 million in operational tasks, which staff say are unlikely to be delivered within one to three years. NZTA has advised it has no funding pathway for evacuation routes or overbridge tsunami assessments, existing council budgets have no spare capacity, and on 11 November Council deferred its citywide resilience fund beyond ten years. Staff ask councillors to weigh three options for the $1.805 million minor improvements package: reallocating money from the Minor Safety and Accessibility programme—which already faces an estimated $20 million backlog and would forgo NZTA co-funding—reviewing funding in the next Long-term Plan round, or deferring the works beyond ten years.

At the same workshop, staff are seeking direction on whether the City Centre Development Incentive Fund—halved through successive annual savings from $500,000 per annum in 2021/22 to $233,250 in its final budgeted year in 2026/27, with zero allocation in the draft 2027–2037 Long-term Plan—should end or continue and potentially expand to other urban centres. While noting high shop vacancies, construction disruption, and sluggish city-centre development, staff cite tight finances ahead of an incoming 4 per cent rates cap, reduced staffing capacity, and the enactment on 18 September 2026 of the Local Government (System Improvements) Amendment Act 2026 removing economic development support from councils' statutory core services, presenting options ranging from no fund to adding two to three full-time-equivalent staff and a $225,000 to $500,000-plus fund ahead of draft Long-term Plan drafting or a 15 December formal report. Elected members will also review an organisation-wide stocktake of external grants, partnerships, sponsorships, community leases, and rates remissions.

## Primary Sources

- **Tauranga City Council** (19 Nov 2026): Agenda (11.0MB pdf) — [Original Document](https://infocouncil.tauranga.govt.nz/Open/2026/11/CWS_20261119_AGN_3044_AT.PDF)