SUPREME COURT OF NEW ZEALAND

Supreme Court dismisses Far North landowners' appeal over Top Energy transmission easements, ruling Minister need not personally consider alternative routes before initiating Public Works Act process

By a four-to-one majority, the Court holds that the Minister for Land Information may rely on a network utility operator's assessment of alternatives when granting a section 186(1) Resource Management Act application, while Chief Justice Winkelmann dissents over an erroneous route statement in the application.

The Supreme Court has dismissed an appeal by three Far North landowners challenging the compulsory acquisition of easements across their properties for a new Top Energy Ltd electricity transmission line between Kaikohe and Kaitaia, holding by a majority that the Minister for Land Information is not required to personally consider alternative routes before initiating the Public Works Act 1981 acquisition process.

Top Energy, the electricity lines company in the Far North of the North Island, obtained most of the required easements along the proposed transmission route by agreement. When three landowners did not agree, the company applied to the Minister for Land Information under section 186(1) of the Resource Management Act 1991 to have the easements acquired or taken under the Public Works Act. The Minister agreed to initiate the process and, after negotiations failed, executed notices of intention to take the easements in June 2017.

The landowners objected to the Environment Court, arguing that Top Energy and the Minister had not properly considered alternatives that avoided taking easements over their lands. The Environment Court resolved the objection in the Minister's favour, holding that the Minister's section 186(1) decision is fully discretionary and that the statutory criteria in section 24(7) of the Public Works Act apply only when the Environment Court hears an objection. On appeal, the High Court found the Environment Court had erred and held the Minister had to personally consider alternatives, whereas the Court of Appeal held the Minister could rely on the utility operator's considerations and need only be satisfied the proposal was capable of meeting the section 24(7) criteria.

Delivering the majority judgment, Justices William Young, Glazebrook, O'Regan and Ellen France concluded that a section 186(1) decision is not fully discretionary and must be exercised reasonably with regard to section 24(7) and the wider statutory scheme. Before granting an application to set the Public Works Act process in train, the Minister must be satisfied on the available information that the network utility operator has articulated its objectives and adequately considered alternatives so that a taking, should it ultimately occur after statutory negotiations and notice, would be fair, sound and reasonably necessary.

The majority held that the Minister is not required to personally consider alternatives at the section 186(1) stage, provided the Minister is satisfied the network utility operator has done so, though the Minister remains free to decline an application or request further information. The majority further determined that reviewing deficiencies in the Minister's section 186 decision-making process falls outside the Environment Court's statutory jurisdiction under section 24(7), which does not confer a judicial review jurisdiction, although the Public Works Act objection mechanism does not preclude judicial review in the High Court and defects in a section 186(1) decision can potentially taint a subsequent taking decision.

In dissent, Chief Justice Winkelmann would have allowed the appeal on the ground that the Environment Court erred in its assessment under section 24(7). While agreeing that the Minister may rely on the network utility operator's consideration of alternatives rather than personally assessing them, the Chief Justice concluded that because granting a section 186 application brings the state's coercive powers of compulsion into play even during purchase negotiations, the Minister must be satisfied before granting the application that the criteria are actually met and that there was a proper reason for selecting the chosen route. On her approach, Top Energy's erroneous statement in its application that the route was the only practical and economic option was a deficiency relevant both to the Minister's decision and to the Environment Court's assessment of whether the taking was fair, sound and reasonably necessary.