South Taranaki District Council will break ground in mid-November on $9.08 million of drinking water treatment and storage upgrades in Ōpunakē and Waverley, bringing the council’s active capital investment across three municipal water plants to nearly $15 million.
In Ōpunakē, the council is investing a projected $6.38 million to construct a new 1,800-cubic-metre treated water reservoir and install Biological Activated Carbon (BAC) treatment technology designed to lift drinking water quality and buffer the coastal town against supply interruptions.
In Waverley, an approximately $2.70 million contract will deliver a new 1,000-cubic-metre treated water reservoir, upgraded pumping systems, an extended treatment building, and a dedicated standby generator to maintain town water supply during power outages and civil defence emergencies. Both projects are scheduled for completion by the end of October 2027, complementing the $5.92 million Pātea Water Treatment Plant upgrade, which is now 75 percent complete.