NZTA schedules 5.5-kilometre Transmission Gully pavement reconstruction following premature surface deterioration

Transport agency overhauls motorway drainage and lays heavy structural asphalt between Paekākāriki and SH58, funding works from the 2024 confidential project settlement.

5.5 kilometres
Pavement reconstruction
Structural asphalt rebuilding on SH1 Transmission Gully
4.5 kilometres
Drainage improvements
Subsurface drainage installation to halt water ingress and cracking
13.8 lane km
Hutt Valley resurfacing
Resurfacing on SH2 from Ngauranga to Maoribank
2024 settlement
Funding source
Reserved from confidential Transmission Gully dispute restructuring

NZ Transport Agency Waka Kotahi has confirmed a major summer maintenance programme for State Highway 1 Transmission Gully (Te Aranui o Te Rangihaeata), initiating 5.5 kilometres of pavement reconstruction and 4.5 kilometres of drainage improvements after road surfaces deteriorated earlier than expected.

Water entering the motorway pavement has accelerated surface cracking and potholing across key sections. Rather than applying seasonal chipseal, road crews will rebuild the underlying foundation using heavy structural asphalt to deliver long-term pavement durability.

Wellington Alliance Manager Roxanne Hilliard said works will occur in two stages: drainage installations in southbound lanes between Paekākāriki and the State Highway 58 interchange starting 8 November and concluding by 18 December, followed by full asphalt reconstruction from 12 January through to March.

Funding for the repairs has been drawn directly from reserves established under the confidential 2024 settlement and restructuring of the Transmission Gully public-private partnership contracts, avoiding additional capital allocations.

Alongside the motorway works, NZTA announced that contractors will resurface 13.8 lane kilometres of State Highway 2 through the Hutt Valley between Ngauranga and Maoribank over five weeks of night operations, managing high-volume corridors carrying more than 34,000 vehicles daily.

“Drainage improvements will help protect the reconstructed pavement from water, while the pavement work will replace the priority sections with stronger structural asphalt.”

Roxanne Hilliard — Wellington Alliance Manager, NZTA