# NZTA schedules two weeks of night works to complete SH6 Rocks Road cliff repairs in Nelson, targeting late November traffic management removal

> Stop-go night repairs from 15 to 26 November will finalise drainage and cliff-face anchors damaged in 2025 winter storms, allowing temporary traffic management to lift before Christmas.

- **Publication:** The Civic Record (Wellington, New Zealand)
- **Desk:** Environment, Transport & Regions
- **Kicker:** NZ TRANSPORT AGENCY WAKA KOTAHI · NELSON HIGHWAY RECOVERY
- **Byline:** Transport & Infrastructure Desk
- **Published UTC:** 2026-11-14T00:00:00+13:00
- **Canonical URL:** https://civicrecord.nz/article/nzta-sh6-rocks-road-cliff-recovery-night-works-2026/

---

## Key Figures

- **Night Schedule:** 10 nights — 15 to 26 November (7pm–6am)
- **Expected Delays:** Up to 10 mins — Between Richardson St & Bisley Ave
- **Night Speed Limit:** 30 km/h — Under active stop/go controls
- **Traffic Management Removal:** Late Nov 2026 — Subject to weather conditions

NZ Transport Agency Waka Kotahi (NZTA) has announced that the State Highway 6 Rocks Road recovery project in Nelson is entering its final operational phase, with two weeks of night works scheduled to complete drainage overhauls and cliff-face stabilisation before temporary traffic management is removed in late November.

The coastal cliff corridor suffered extensive damage during winter storms in June and July 2025. NZTA Nelson/Tasman Area Manager Rob Service confirmed that major structural engineering milestones have now been achieved: shotcrete has been fully applied across the cliff face, drilling is complete, all anchors and subsurface drains are installed, and construction of a retaining wall on NZTA-owned land atop the cliff is nearing completion.

Contractors have begun disestablishing their temporary construction compound at the Basin Reserve. To conclude the works, crews will operate on site for 10 nights between Sunday 15 November and Thursday 26 November, concluding at 6:00 am on Friday 27 November. Stop-go traffic management and a temporary 30 km/h speed limit will apply between 7:00 pm and 6:00 am, with delays of up to 10 minutes expected between Richardson Street and Bisley Avenue.

Night operations will focus on milling and replacing damaged asphalt, repairing concrete kerbing, cleaning drainage systems, repairing stormwater sumps and gratings, installing specialised anchor plates and bolts, applying protective weather wrapping by hand, and erecting permanent fencing along the cliff top. Daytime construction continues Mondays to Saturdays, with the entire project on track for full completion before Christmas.

> "This is an important milestone for the project. Work at the southern end is complete, all shotcrete has been applied to the cliff face, and drilling has finished, with all anchors and drains now installed."
> — **Rob Service**, Area Manager – Nelson/Tasman, NZ Transport Agency Waka Kotahi

## Primary Sources

- **NZ Transport Agency Waka Kotahi** (12 Nov 2026): Final stages underway for State Highway 6 Rocks Road recovery project — [Original Document](https://www.nzta.govt.nz/media-releases/final-stages-underway-for-state-highway-6-rocks-road-recovery-project)