# Hawke's Bay Regional Council begins 3km Waipawa River stopbank upgrade under $30 million programme

> Construction commences on raising and widening flood barriers along the Waipawa River true-left bank to a 1% Annual Exceedance Probability standard, reusing 60,000 cubic metres of river channel gravel.

- **Publication:** The Civic Record (Wellington, New Zealand)
- **Desk:** Local Government, Flood Defence & Conservation
- **Kicker:** HAWKE'S BAY REGIONAL COUNCIL · CENTRAL HAWKE'S BAY · FLOOD RESILIENCE
- **Byline:** Hawke's Bay Regional Council (Te Kaunihera ā-Rohe o Te Matau-a-Māui)
- **Published UTC:** 2026-11-01T00:00:00+13:00
- **Canonical URL:** https://civicrecord.nz/article/hawkes-bay-rc-waipawa-stopbank-upgrade-2026/

---

## Key Figures

- **Regional stopbank programme:** $30 million — Total budget allocated by HBRC to strengthen stopbanks across the region
- **Waipawa stopbank length:** 3 kilometres — Stopbank upgrade along the true-left bank from Coronation Park to Rathbone Street
- **Dredged gravel reuse:** 60,000 m³ — Gravel excavated from the river channel for use in stopbank engineering
- **Protection design standard:** 1% AEP — Designed to withstand a 1-in-100-year flood event plus freeboard allowance

Construction has begun on a major upgrade of Waipawa's river stopbank network as part of Hawke's Bay Regional Council's $30 million regional programme to reinforce flood defences following Cyclone Gabrielle.

The project will raise and widen three kilometres of earthen stopbank along the true-left bank of the Waipawa River, extending from Coronation Park to Rathbone Street. Based on updated hydrodynamic flood modelling, the height of the barrier will be increased by amounts ranging from several centimetres to up to two metres above previous levels.

Tamatea/Central Hawke's Bay constituency councillor Tony Kuklinski noted that floodwaters breached the stopbank at Coronation Park during Cyclone Gabrielle, damaging homes and severing town access. Raising the structure is intended to prevent channel breakout during major rainfall events.

The upgraded defences are engineered to contain a 1% Annual Exceedance Probability (AEP) flood—the regional benchmark corresponding to a one-in-100-year event—with an additional freeboard height buffer to absorb climate change projections and modelling variance. Approximately 60,000 cubic metres of gravel excavated from the Waipawa River bed will be repurposed as engineered fill in the embankment, simultaneously clearing the river channel.

Earthworks are scheduled to continue through to autumn 2027, followed by topsoiling, grass seeding, and the reinstatement of the riverside limestone public walking track.