Environment Canterbury nears completion of $2.4m Courtenay floodgate replacement, improving Kaiapoi drainage and native fish passage

A $2.4 million infrastructure upgrade replacing 1940s earthquake-damaged floodgates at the confluence of Courtenay Stream and the Kaiapoi River is scheduled for completion this month, improving flood resilience for the lower Waimakariri while installing fish-friendly side-hung gates.

$2.4m
Total investment
Co-funded by the Government's Regional Infrastructure Fund (administered by Kānoa) and Environment Canterbury
4 metres
Stopbank path width
Retains walking and cycling connection over structure
February 2026 start; on track for November finish
Construction timeline
Replaces 1940s structure that suffered significant earthquake damage in 2011

A $2.4 million project to replace the ageing Courtenay floodgates near Kaiapoi is nearly complete, after construction began in February 2026 and remains on track to be finished in November. The project received co-funding from the Government's Regional Infrastructure Fund, administered by Kānoa – Regional Economic Development & Investment Unit, and Environment Canterbury.

The engineering works replace an ageing floodgate dating back to the 1940s that suffered significant earthquake damage in 2011, caused by liquefaction and ground settlement.

Situated where Courtenay Stream meets the Kaiapoi River, the floodgate operates automatically according to water levels, with no mechanical operating system required. The gates open to let water drain out and close when river levels or tides are high enough to push water back upstream.

The new side-hung gates will remain open for longer periods and provide a wider, more natural opening than the existing structure, improving fish passage for species such as īnanga (whitebait), although the gates still need to close during high tides to prevent flooding. The old gates required frequent debris clearing and exposed staff to risks including steep access and confined spaces. Restorative planting is also proposed around the completed site, including planting intended to add īnanga spawning habitat.

Councillor Ian Mackenzie, Environment Canterbury's Community Preparedness and Response to Hazards Core Service Lead, said replacing ageing infrastructure is an important part of preparing for the future. The stopbank walking and cycling connection is being retained over the top of the new structure, including the four-metre-wide stopbank crest.

“Replacing this flood gate is an important part of that programme and will contribute to keeping our communities around the lower Waimakariri safe and dry.”

Ian Mackenzie — Hazards Core Service Lead Councillor, Environment Canterbury