# Electricity Authority schedules mandatory five-year ASX baseload futures quoting from 1 March 2027 with 8 MW far-dated offer volume

> Implementing an April 2026 market-making decision, the regulator has set out 2027–2029 quoting schedules extending mandatory quarterly baseload electricity futures quotes from three to five years ahead on the ASX.

- **Publication:** The Civic Record (Wellington, New Zealand)
- **Desk:** Business, Energy & Primary Sector
- **Kicker:** ELECTRICITY AUTHORITY · WHOLESALE FUTURES MARKET
- **Byline:** Energy & Regulation Desk
- **Published UTC:** 2026-11-17T11:00:00.000Z
- **Canonical URL:** https://civicrecord.nz/article/ea-schedules-five-year-asx-baseload-market-making-march-2027/

---

## Key Figures

- **Mandatory quoting horizon:** 5 years — Extended from 3 years ahead for quarterly ASX baseload electricity futures from 1 March 2027
- **Far-dated offer volume:** 8 MW — Reduced from 12 MW total offer volume requirement for contracts expiring three to five years out
- **Required quotes per session:** 24 / 16 — 24 quotes for current plus two calendar years (8 quarters); 16 quotes for following three years (12 quarters)

From 1 March 2027, wholesale electricity market makers will be required to provide quotes for quarterly baseload electricity futures on the ASX out to five years ahead, extending the current three-year horizon, the Electricity Authority Te Mana Hiko advised on 17 November 2026. The regulator—which decided on the Code changes in April 2026—said extending mandatory quoting will make forward prices available further into the future to help market participants plan and manage electricity price risk.

Alongside extending the quoting horizon from three to five years ahead, the changes reduce the total offer volume requirement from 12 MW to 8 MW for baseload contracts with expiry dates three to five years out. Although the ASX listed additional contracts for 2031 and 2032 on 12 October 2026, quoting prices on those contracts remains voluntary and existing market-making rules continue to apply until 1 March 2027, with market makers advised to prepare their quoting systems ahead of the transition.

Under the three-year session schedule set out by the Authority, each market maker must provide 24 quotes per contract at 2.4 MW required volume for the current calendar year and the following two years (eight quarters), and 16 quotes per contract at 1.6 MW required volume across the subsequent three calendar years (12 quarters)—covering 2027–2029 and 2030–2032 during the remainder of 2027 before rolling forward annually through 2028 and 2029. As the ASX lists new quarterly contracts each 1 October, mandatory quoting for each newly listed year will begin the following January.

## Primary Sources

- **Electricity Authority (Te Mana Hiko)** (17 Nov 2026): Baseload market making changes from March 2027 — [Original Document](https://www.ea.govt.nz/news/general-news/baseload-market-making-changes-from-march-2027/)