Regulators say tighter scrutiny may be needed on $600m–$700m grid exit substation investments that could add around $200–$300 to annual household power bills

A joint Commerce Commission and Electricity Authority inquiry finds local distribution lines companies are committing to major grid connection projects without adequately testing battery storage, flexible demand, or cost-benefit alternatives.

$600m–$700m
Pipeline Investment Value
In GXP projects currently in development
$200–$300/yr
Household Bill Exposure
Potential annual impact per household from a single GXP
4 distributors
Distributors Audited
In sample assessment of EDB investment proposals
15 December 2026
Submissions Deadline
Consultation closes at 5:00 pm

A review led by the Commerce Commission for the Energy Competition Task Force suggests new regulatory measures and scrutiny may be needed for major local electricity distribution substation projects, with around $600 million to $700 million in grid exit point (GXP) investments currently being investigated, developed, or delivered.

The joint inquiry, conducted by the Commerce Commission and the Electricity Authority alongside observers from the Ministry of Business, Innovation and Employment, examined grid exit point (GXP) investments across four local electricity distribution businesses. GXPs represent critical substations where electricity transfers from Transpower's national grid into local distribution networks.

Unlike other transmission grid projects, distributor-initiated GXP investments do not receive the same regulatory scrutiny. However, the Task Force noted that a single GXP investment could add around $200 to $300 a year to the electricity bill of an average household in some regions.

While the review found examples of good practice across the sector, it found limited evidence that alternative solutions—including flexible demand options, demand response, distributed energy resources, battery storage, and staged investment approaches—had been fully explored in some cases. It also found limited information on customer preferences, consumer willingness to pay, pricing signals, and cost-benefit analysis.

Commerce Commission Chair Dr John Small and Electricity Authority General Manager of Networks and System Change Tim Sparks stated that clearer cost signaling and rigorous testing of alternative solutions are vital to prevent unnecessary network overbuilding. The Task Force has opened a public consultation on potential regulatory reforms running until 5:00 pm on Thursday 15 December 2026.

“GXP projects do not get the regulatory scrutiny of other transmission grid projects, but a single GXP investment could add around $200 to $300 a year to the electricity bill of an average household in some regions. With electricity already a major cost for consumers, it’s essential these investments genuinely stack up and that alternatives are actively considered.”

Dr John Small — Chair, Commerce Commission New Zealand