Clutha District Council tables $15.45m water transition programme and reallocates roading funds for $1.4m Chaslands Highway slip repair, while contractor disputes Milton pavement liability

Forty of the council’s 79 Three Waters capital projects—representing 71 per cent of the $15.45 million budget—remain in scoping or investigation ahead of the 1 July 2027 handover to Southern Waters, while surplus pre-seal funds will cover an engineer’s estimate overrun on Chaslands Highway and up to $750,000 may go unspent on the Milton Streetscape.

$15.45m
Three Waters capital budget
Across 79 projects; 40 projects ($10.95m, or 71%) at scoping or investigation stage
~$1.4m
Chaslands Highway slip estimate
Engineer’s estimate of around $1,400,000 against $550,000 original allocation
Up to $750,000
Milton Streetscape unspent budget
$1,500,000 forecast cost against $2,250,000 total budget

Clutha District Council is managing a 79-project, $15.45 million Three Waters capital programme ahead of the scheduled 1 July 2027 transfer of three waters assets and services to Southern Waters, while reallocating roading funds to cover a sharp cost increase on Chaslands Highway and carrying interim costs in a disputed contractor liability decision in Milton. Across the water capital portfolio tabled for the council’s Risk and Assurance Committee meeting on 26 November 2026, 40 projects accounting for $10.95 million—or 71 per cent of the combined budget—remain at the scoping or investigation stage, alongside 26 projects worth $2.51 million in implementation and 13 worth $1.99 million that are complete or closing.

Although council staff rate the Three Waters capital programme on track overall ahead of an end-of-February 2027 programme review with Southern Waters, regulatory compliance and staff resourcing remain classified as high risks. Abatement notices are in place at Moa Flat, the discharge consent for the Clinton wastewater treatment plant expires on 5 May 2027, and Otago Regional Council may require further work at the Clydevale bore. Major items across the 58 water supply, 16 wastewater, and five stormwater projects include preliminary design on a $3.50 million Puerua water treatment plant renewal—whose physical works and remaining budget will carry forward to Southern Waters in 2027/28—capacity testing and pricing on a $1.99 million Milton (Milburn) water treatment plant upgrade, and $0.92 million across eight rural zone-metering projects set to go to tender for smart water meters in December 2026. Over the first quarter of 2026/27 to 30 September 2026, Three Waters operating expenditure totalled $7.39 million against a $7.6 million budget—an underspend of $0.21 million, or 2.80 per cent, partially offset by higher legal and resource management costs—producing an operating surplus of $1.16 million compared with a budgeted $1.07 million.

Preparations are also advancing under the Southern Water Done Well transition process on the schedules to the legal Transfer Agreement that will shift water services assets, debt, liabilities, and responsibilities from the council to Southern Waters, ahead of a Council Debt Notice due on 1 June 2027. On 10 November, the Programme Director and HR Transition Lead met staff in person to outline milestone dates and assessment pathways into the new organisation, with formal staff consultation starting the week of 18 January 2027, final decisions expected in late March 2027, and formal job offers scheduled for April 2027.

In Milton, the council faces both a pavement damage dispute and redesigned underground pipe renewals. On the North Milton State Highway 1 pipeline renewals—with completion forecast for 8 December 2026—minutes from the committee’s 15 October 2026 meeting record that the Independent Certifier found the contractor liable for Union Street pavement damage, that the contractor disputed the decision and had until 8 December 2026 to seek a review, and that the council would carry the project costs until responsibility and recovery were resolved. Those minutes also note that Fulton Hogan would undertake the Union Street resealing as a subcontractor to Isaac Construction, while full reinstatement and resealing of the detour route was excluded from the project forecast and deferred to the council’s reseals programme after Christmas–New Year; a further report on the North Milton State Highway 1 pipeline renewals is listed for public-excluded consideration on 26 November 2026 on grounds of commercial sensitivity under the Local Government Official Information and Meetings Act 1987.

Elsewhere in Milton, the council has agreed in principle to a revised design engagement with consultant GHD costing approximately $107,642 excluding GST—covered within the existing $1,529,138 project budget—to assess moving the Milton asbestos cement water main renewal into the road reserve after an affected landowner opposed access through private property, while also adding a previously excluded KiwiRail crossing and geotechnical investigations. That redesign moves target tender release to 30 March 2027, target tender award to May 2027, and construction to June–November 2027, extending into the 2027/28 financial year. Detailed design is complete on the separate $1,148,135 Milton concrete water main renewal—covering Priority 1 assets assessed as in extremely poor condition and at high risk of imminent failure—but tender release has been delayed until the current-year budget allocation is fully reflected in the council’s financial system, while staff also flag a risk that the $2,110,870 Milton stormwater renewal will not be delivered within 2026/27 following a delay in receiving the scope of works. By contrast, the rates-funded Milton Streetscape project is forecast to cost $1,500,000 against a $2,250,000 budget, leaving up to $750,000 in estimated unspent funds that may be returned to the council on completion, although planting might need to be deferred until autumn 2027 (April–May) after the contractor’s previous plant supplier closed.

Across the district’s transport, waste, and corporate systems, consultant WSP’s engineer’s estimate of around $1,400,000 for permanent slip remediation at RP 11.0 on Chaslands Highway—damaged in an October 2024 rainfall event—exceeded the original $550,000 budget allocation by more than 15 per cent; following a contractor due diligence review by Currie Construction Limited confirming the design is fit for purpose and WSP’s pricing rates are reasonable, the council’s Transport Operations team agreed on 16 November 2026 to cover the shortfall using surplus Work Category 111 pre-seal repair funding without reducing the wider transport programme. Separately, the council is advancing a $1,700,000 bridge repair programme funded through existing council and New Zealand Transport Agency provisions—after inspections identified more than 100 defects across 93 bridges beyond available repair budgets—and advertised a Request for Proposal on 10 November 2026, closing 4 December 2026, to select two contractors for an Early Contractor Involvement process covering capital works and operations at the Mt Cooee landfill alongside district-wide kerbside collection. Internally, integration and reporting difficulties with the Datascape financial system, coupled with roading financial complexities, delayed website publication of the council’s Annual Report beyond its 31 October 2026 requirement—with the report scheduled to go to the council for adoption on 26 November 2026—and held up Resource Management Act National Monitoring System disclosures, prompting Datacom specialists to be scheduled onsite for the week commencing 7 December 2026.