Christchurch City Council has reported initial signs of biological recovery across the Christchurch Wastewater Treatment Plant oxidation ponds, alongside accelerating construction milestones on the long-term activated sludge facility.
some key indicators have improved, with conditions stabilising over the past few days.
A number of concrete pours are scheduled before Christmas to complete key sections of the new plant. The council says that as temperatures increase, pours need to take place early in the morning when it is cooler, to ensure the concrete meets quality requirements.
Work on the earth bund is progressing, with the existing bund now covered in topsoil and mulch and the extension becoming more visible each day. Irrigation is being installed and the area prepared for planting, and the planting crew is due on site mid-next week to begin planting native plants. Once complete, the project will provide a greener boundary around the plant and improve the outlook from neighbouring properties.
The council's odour monitoring network recorded some elevated odour readings over the past week, though all hydrogen sulphide readings remained below the 0.03 parts-per-million threshold. The last reading above that level occurred on 25 October and was likely associated with maintenance activity elsewhere at the treatment plant rather than the oxidation ponds themselves. The council continues to encourage anyone who notices an odour to report its location and strength through the Smelt-it platform.