Christchurch City Council staff are consulting five affected community boards on whether decision-making powers for parking removal, bus stop changes, and turning restrictions along the city's core public transport corridors should be centralised with the full Council as matters of metropolitan significance, beginning with an estimated $33.4 million to $36.6 million infrastructure upgrade across Routes 1 and 5.
Set out in workshop agendas and the single stage business case prepared for community board information sessions in late November 2026—including the Waipuna Halswell-Hornby-Riccarton Community Board workshop on 24 November 2026—the preferred programme covers Route 1 (Belfast to Cashmere via Papanui Road and Colombo Street) and Route 5 (Hornby to New Brighton via Riccarton Road). The two corridors carry approximately 90,000 and 120,000 passenger trips per month respectively, but both currently operate at around 77 per cent on-time performance against NZTA Waka Kotahi's 85 per cent target, with bus journeys typically taking 30 to 70 per cent longer than equivalent private car trips.
To meet investment objectives of reducing peak bus journey-time variability by 20 per cent and average peak in-vehicle travel time by 10 per cent by 2030, the business case proposes five integrated components across 15 delivery packages. Core physical works comprise approximately 14 kilometres of new or extended bus lanes, signal-controlled bus advances, and queue jumps. Four complementary corridor-wide packages add a net reduction of 60 bus stops from the existing 270 stops alongside upgrades to approximately 38 receiving stops, extended operating hours on 13 existing bus lanes (12 to both weekday peaks and one throughout the weekday), adaptive traffic-signal priority for late-running buses, and a staged camera-first enforcement programme deploying 32 solar cameras from day one, 18 travel cameras, and 19 further solar cameras after construction.
The business case estimates a P50 capital cost of $33.4 million and a P95 capital cost of $36.6 million, alongside incremental operating costs of approximately $1.1 million per year, while the accompanying community board briefing reports place the expected programme cost at about $33.7 million. Route 5 accounts for around 81 per cent of the capital cost—about $27 million—because it currently has less bus priority infrastructure and requires larger physical works, yielding a route-level benefit-cost ratio of 2.3 compared with 6.2 for Route 1 and 3.3 for the combined programme.
NZTA Waka Kotahi endorsed the business case on 17 September 2026 and approved co-funding at a 51 per cent Funding Assistance Rate for the pre-implementation design and engagement phase in 2026/27, which is budgeted at approximately $3.2 million to $3.3 million. However, the remaining construction funding of approximately $30 million to $30.2 million must be sought through the 2027–30 National Land Transport Programme and is not yet approved, and the Council itself has made no formal decision on the programme following an initial information briefing on 17 November 2026.
Under the Council's current Delegations Register, the full Council decides bus lanes and their operating hours, while individual community boards decide associated parking removals, bus stop relocations, turning restrictions, kerb build-outs, and bus shelters within their boundaries. In August 2026, staff proposed that public transport projects on defined core routes be treated as matters of metropolitan significance decided solely by the Council, but the Executive Leadership Team declined to endorse the proposal on 13 August 2026 and directed staff to seek feedback from the affected boards first.
Community boards are being asked to submit feedback by 8 December 2026 on three governance options: transferring decision-making to the Council for all defined Tier 1A and Tier 1B core network routes, transferring decisions to the Council for Routes 1 and 5 only, or retaining current split delegations. All five boards' feedback is scheduled to go to the Executive Leadership Team in February 2027 before any governance report goes to the Council in early 2027, with developed corridor designs to return for public consultation later in 2027 ahead of staged construction planned from 2027/28 to 2029/30.