Auditor-General finds Auckland Council managed $53m Māngere flood protection projects well, while noting need for consolidated programme reporting

The Office of the Auditor-General concludes that Auckland Council maintained a consistent focus on value for money and generally followed the principles and good practices in the Government Procurement Rules across the fast-tracked Harania Creek and Te Ararata Creek projects, though flood risk reductions cannot be confirmed until construction finishes and updated assessments are carried out.

$53m
Combined project budget
62 per cent funded by the Government and 38 per cent by Auckland Council
About 376
Properties with reduced flood risk
Including 56 assessed as facing an intolerable risk to life
About 85%
Share of Auckland's wastewater carried by pipe being worked on
Share of Auckland's wastewater carried by a major pipe worked on during the projects
285
Wildlife relocated
Copper skinks re-homed by the end of 2025

The Office of the Auditor-General has found that Auckland Council managed its first two blue-green flood protection projects in Māngere well, maintaining a consistent focus on value for money while balancing urgent deadlines against cost controls. In its assessment of the Harania Creek and Te Ararata Creek projects, the watchdog concluded that the council generally followed the principles and good practices in the Government Procurement Rules, identifying only minor improvements that were shared directly with the council.

Designed following the severe flooding of the January and February 2023 Anniversary weekend storms and Cyclone Gabrielle, the two projects aim to reduce flood risk to about 376 surrounding properties. Of those properties, 56 were assessed as facing an intolerable risk to life and would have been compulsorily acquired under the Government's buy-out scheme had the projects not proceeded. The works carry a combined budget of $53 million—funded 62 per cent by the Government under severe weather recovery arrangements and 38 per cent by the council—with a funding deadline for completion by mid-2026.

The technical works involve replacing a bridge owned by Auckland Transport, relocating lizards and fish, and carrying out work on a Watercare pipe that carries about 85 per cent of Auckland's wastewater, alongside sites with active Vector power lines and many affected properties owned by Kāinga Ora. To reduce uncertainty for residents and meet the mid-2026 funding deadline, consenting was fast-tracked through a Cabinet-approved Order in Council under the Severe Weather Emergency Recovery Legislation Act 2023, modifying Resource Management Act 1991 requirements. Resource consents were granted in December 2024, site possession occurred in May and July 2025, and final construction contracts were signed in August 2025.

With Government approval, the council sourced two preferred suppliers directly from a pre-existing stormwater supplier panel established under Master Service Agreements signed in 2022. To protect value for money during direct sourcing and early contractor involvement, the council required open-book pricing, imposed a maximum budget affordability threshold, and used an independent surveyor to review supplier proposals and benchmark their pricing, with an independent advisor reviewing suppliers' prices between March and May 2025. The council also noted past examples where early contractor involvement participants were not awarded final construction contracts because their quoted prices were too high.

Delivery risk was governed through NZS 3910:2013 contracts with special conditions limiting contractor claims for additional time or costs on issues that should have been identified earlier, supported by independent contract administrators and site cameras for real-time and time-lapse monitoring. Following a late-2024 internal audit that identified governance weaknesses in the wider Making Space for Water programme—including unclear role definitions, gaps in early decision-making records, and the lack of a council-wide governance framework—the council introduced a formalised governance framework and strengthened project-level oversight in 2025. Dual accountability is provided by the council's Transport, Resilience, and Infrastructure Committee and by National Infrastructure Funding and Financing, which reviews milestones before releasing Government funds.

While governors and funders expressed confidence in the quality of information the council provides, partner organisations were positive about its engagement, and the Auditor-General considered the council had communicated well with the public — including through a monthly stakeholder advisory group, mana whenua design input, and an end-of-2025 update recording the re-homing of 285 copper skinks — the Auditor-General noted that the council could consolidate key project information into a single document for decision-makers. Although staff reported that the project management system generates consolidated reporting for senior management, the Auditor-General had not yet seen examples, and noted that the council cannot confirm it has achieved its flood risk reduction aims until construction finishes and updated flood risk assessments are completed.

“In procuring and managing the projects, the Council has consistently focused on value for money. We saw that the Council designed its approach to achieve the best possible outcomes with the resources available and took active steps to balance the need for urgency with the need to manage costs.”

Office of the Auditor-General — Parliamentary report